Works announcement and traffic disruption

Work in progress

Place Pestalozzi – Centre Ville
Eclairage public, pavage, bornes accès, électricité basse tension (tableau pour animations)
Durée estimée : 10 mois, février – novembre 2017

Rue de Montchoisi
General rehabilitation of the underground infrastructure and the roadway
Estimated duration: 6 months, June - December 2017

Rue du Levant
Repair of water and gas pipes, electricity, public lighting
Estimated duration: 8 months, end of August 2017 - April 2018

Rue du Midi
Redevelopment work on Rue du Midi, from Canal Oriental to Rue des Moulins, including Rue Roger-de-Guimps between Rue du Midi and Rue des Jordils.
Notice of 25 August 2016 - Accepted by the Municipal Council on 6 October 2016
Services concerned: Yverdon-les-Bains Energies - Service des Travaux et de l'Environnement
Estimated duration: June 2017 - November 2018

More information is available on the page dedicated to the Rue du Midi construction site.

 

For any contact concerning the aforementioned building sites: A. Favre(afa@ylb.ch)

Finishing worksites

When a construction site is completed, Yverdon-les-Bains Énergies must respect a deadline before the final covering is laid. For technical reasons, the laying of this covering is generally done between May and July.

The streets concerned by the installation of the finishing coat planned for 2017 are:

– Rue de la Roselière
– Rue des Chainettes (Est)
– Rue de la Jonction
– Route de Bellevue
– Chemin des Sources 50-58
– Rue des Petites Roches

Last updated: March 29, 2019 at 3:46 pm