Since mid-May, Yverdon-les-Bains Énergies has been coordinating the Rue du Midi construction site. The redevelopment of this street, from the Canal Oriental to the rue des Moulins, and the rue Roger-de-Guimps between the rue du Midi and the rue des Jordils requires nearly 600 m of excavation and work: a complex and delicate site!
After the first month of construction, several works have already been carried out and the site is proceeding according to schedule.
Work completed to date :
- Installation of temporary water and gas connections for all houses since 15 May.
- Crossing under the Oriental Canal made for gas and water
- Dismantling of the covered garages of the Midi car park - The first timelaps of the construction site!
- Expansion of the Gravelines-Trois-Lacs bend
- Moderation at 30Km/h on Gravelines
Throughout the worksite, open days are organised by Yverdon-les-Bains Énergies to inform local residents about the progress of the worksite. The first session will take place on Wednesday 5 July from 5:00 pm to 7:00 pm at the Parking du Midi in Implénia's construction site facility.
The next dates will be available on the page dedicated to the construction site or on the Service's Facebook page.